Preparation of Brick Earth
It consists of the following operations.
Unsoiling: The soil used
for making building bricks should be processed so as to be free of gravel, coarse sand (practical size more than 2 mm), lime and kankar particles, organic matter, etc.
About 20 cm of the top layer of the earth, normally containing stones, pebbles,
gravel, roots, etc., is removed after clearing the trees and vegetation.
Digging: After removing
the top layer of the earth, proportions of additives such as fly ash, sandy
loam, rice husk ash, stone dust, etc. should be spread over the plane ground
surface on volume basis. The soil mass is then manually excavated, puddled,
watered and left over for weathering and subsequent processing. The digging
operation should be done before rains.
Weathering: Stones, gravels, pebbles, roots, etc. are removed from the dug earth
and the soil is heaped on level ground in layers of 60–120 cm. The soil is left
in heaps and exposed to weather for at least one month in cases where such weathering is considered necessary
for the soil. This is done to
develop homogeneity in the mass of soil, particularly if they are from
different sources, and also to eliminate the impurities which get oxidized.
Soluble salts in the clay would also
be eroded by rain to some extent,
which otherwise could
have caused scumming at the time of burning of the bricks in the kiln. The soil should be turned over at least twice and
it should be ensured that the entire soil is wet throughout the period of weathering. In order to keep
it wet, water may be sprayed as often as necessary. The plasticity and strength of the clay are improved by exposing the clay to weather.
Blending: The earth is then mixed
with sandy-earth and calcareous-earth in suitable proportions to modify the composition of soil. Moderate
amount of water
is mixed so as to obtain the right
consistency for moulding. The mass is then mixed uniformly with spades.
Addition of water to the soil at the dumps is necessary for the easy mixing and
workability, but the addition of water should be controlled in such a way that
it may not create a problem in moulding and drying. Excessive moisture content
may effect the size and shape of the finished
brick.
Tempering: Tempering consists of kneading the earth with feet so as to make the mass stiff
and plastics (by plasticity, we mean the property which
wet clay has of being
permanently deformed without cracking). It should preferably be carried out by storing
the soil in a cool place in layers
of about 30 cm thickness for not less than 36 hours. This will ensure
homogeneity in the mass of clay for subsequent processing. For manufacturing
good brick, tempering is done in pug mills and the operation is called pugging.
Moulding
It is a process of giving a required shape to the brick from the prepared brick earth. Moulding
may be carried out by hand or by machines. The process of moulding of bricks may be the soft-mud (hand
moulding), the stiff-mud (machine moulding) or the dry- press process (moulding
using maximum 10 per cent water and
forming bricks at higher pressures). Fire-brick is made by the soft
mud process. Roofing, floor and wall
tiles are made
by dry-press method. However,
the stiff-mud process is
used for making all the structural clay products.
Drying
Green bricks contain about 7–30% moisture depending upon the
method of manufacture. The object of drying is to remove the moistre to control
the shrinkage and
save fuel and
time during burning. The drying shrinkage is dependent upon
pore spaces within the clay
and the mixing water. The addition of
sand or ground burnt clay reduces shrinkage, increases porosity and facilities drying. The moisture content is brought down to
about 3 per cent under exposed conditions within three to four days. Thus, the
strength of the green bricks is increased and the bricks can be handled safely.
Clay
products can be dried in open air driers or in
artificial driers. The artificial driers are of two types, the hot floor drier and the tunnel drier. In the former,
heat is applied
by a furnance placed at one end of the drier or by exhaust steam from the
engine used to furnish power and is used for fire bricks, clay pipes and
terracotta. Tunnel driers are heated
by fuels underneath, by steam pipes,
or by hot air from cooling
kilns. They are more economical than floor driers.
In artificial driers, temperature rarely exceeds 120°C. The time
varies from one
to three days.
In developing countries,
bricks are normally dried in natural open
air driers (Fig. 2.8). They are stacked on raised ground
Burning
Kiln Burning:
The kiln used for burning bricks may be
underground, e.g. Bull’s trench kiln or overground, e.g. Hoffman’s kiln.
These may be rectangular, circular
or oval in shape. When the
process of burning bricks is continuous, the kiln is known as continuous kiln, e.g. Bull’s trench
and Hoffman’s kilns. On the other hand if the process of burning bricks is
discontinuous, the kiln is known as intermittent kiln.
Intermittent Kiln: The example of this type of an over ground, After loading the kiln, it is fired,
cooled and unloaded
and then the next loading
is done. Since the walls and
sides get cooled during reloading and are to be heated again during next
firing, there is wastage of fuel.
MANUFACTURING PROCESS OF BRICK
Reviewed by SANTHOSH KUMAR
on
July 08, 2018
Rating:
No comments: