Compaction - Methods:
Concrete should be placed and compacted immediately after
mixing. The concrete should be placed within 30 to 40 minutes to prevent the
danger of concrete getting its initial set, before laying the concrete, the
shuttering should be cleaned of all of dust or debris. Crude oil or grease etc
is usually applied to the shuttering before concreting to prevent the
shuttering absorbing the water from the concrete or getting struck to it. In
placing the concrete, care should be taken to see that it should not be
thrown from heights. Concrete should be laid in layers 15 to 30 cm (6” to 12”)
in thickness and each layer should be properly compacted before laying the next
one. Compaction of concrete should be proceed immediately after
placing. The function of compaction of concrete is to expel the air bubbles in
the mass and make it impermeable in addition to its securing the desired
strength. The concrete mass should be consolidated or compacted till the cream
of the cement starts appearing on the surface. Over compaction may lead to segregation
of concrete while-under-compaction may leave air voids in concrete and results in honey combing. Compaction
may be done by hand or mechanical device.
(i) Hand
compaction: The hand
compaction may be done by rodding, tamping or hammering. Tamping is usually
adopted for compacting concrete for slabs or other such surfaces. Rodding is
done for thin vertical members. Hammering is done for massive plain concrete
works and for compacting an almost dry
concrete the surface is beaten with heavy flat bottom rammers
till the thin film of mortar start appearing on the surface.
(ii) Mechanical compaction: Mechanical compaction is done by
the use of vibrators.
Vibrators are of three types
1. Internal
2. External
3. Surface.
Internal vibrators
are commonly used in large works for flat surface compaction. In this the
vibrator is immersed in the full depth of concrete layer. The vibrator should be
kept in one position for about 3 minutes and then removed and placed another position.
External vibrators are placed against
the form work and are only adopted for thin section of members or in places where
internal vibrators cannot be used with ease. Surface vibrators are generally
employed in concrete road construction. Compaction of concrete by use of vibrators
permits the use of stiff concrete mix of high strength and ensure better compaction
than that obtained by the method of hand compaction